Supreme Court of India

UNION OF INDIA & ORS v. GOPALDAS BHAGWAN DAS & ORS

Supreme Court dismisses Union of India appeal; s.4 notification struck down in Kulsum Nadiadwala applies here

The Court dismissed the Union of India's appeal and upheld the Bombay High Court's decision. It did not answer the referred question on delay and laches, holding that the s.4 notification was the same one struck down in Kulsum R. Nadiadwala, and that the matter could not be adjourned pending the Constitution Bench in Indore Development Authority.

Why it matters: The Court held that a land acquisition notification struck down in an earlier case cannot be upheld for another land under the same notification, as this would discriminate between similarly placed persons.

Summary written with AI and checked against the judgment text. It is not part of the judgment; read the full text or PDF.

Headnote

Land Acquisition Act, 1894 – ss.4(1), 6 – In 1943, Govt. of India requisitioned 4 acres and 34 gunthas of land bearing Survey No. 120/2 (Part) of Village Malad, Mumbai – In 1949, 2.68 acres land out of the aforesaid land was de-requisitioned – In 1975, notification was extent of 8623 sq.m. – Declaration u/s.6 issued in 1978 – Draft Award passed in 1986 – Challenge made in the present case in the year 2002 – In a proceeding concerning other lands covered by the same s. 4 notification, Supreme Court in Kulsum R. Nadiadwala v. State of

Headnote as published with the judgment in the Supreme Court Reports dataset; it is not part of the judgment.
Court
Supreme Court of India
Case number
CIVIL APPEAL No. 3636/2016
Date of judgment
4 February 2020
Petitioner / Appellant
UNION OF INDIA & ORS
Respondent
GOPALDAS BHAGWAN DAS & ORS
Neutral citation
2020 INSC 127
SCR citation
[2020] 3 S.C.R. 765
Bench
R.F. NARIMAN, S. RAVINDRA BHAT, V. RAMASUBRAMANIAN
CNR
ESCR010002402020
Result
Dismissed
Download PDFFind it on the Supreme Court SCR siteGet the signed copy

Signed copy from the Supreme Court. On the court's Judgments page, open the Case Number tab, choose the case type Civil Appeal, enter the case number 3636 and the year 2016, solve the captcha, and open the PDF in the Judgment column. Or use the Judgment Date tab with 04-02-2020 as both dates. The court's page asks for a captcha, so this step is yours.

This is the Supreme Court Reports (SCR) copy, with citation and headnotes, obtained through the Indian Supreme Court Judgments open dataset (CC-BY-4.0, Dattam Labs) and unchanged. To find it on the Supreme Court's own SCR site (scr.sci.gov.in), enter the neutral citation 2020 INSC 127 in its Neutral Citation field. It is not the plain signed judgment and not a certified copy; for a certified copy use the Certified Copy service on sci.gov.in. The text below is extracted automatically and may contain errors, and the result label is read from the closing lines of the judgment, so it can occasionally be wrong. The PDF is the authoritative version.

A

B

C

D

E

F

G

H

765

UNION OF INDIA & ORS.

v.

GOPALDAS BHAGWAN DAS & ORS.

(Civil Appeal No. 3636 of 2016)

FEBRUARY 04, 2020

[R. F. NARIMAN, S. RA VINDRA BHAT AND

V. RAMASUBRAMANIAN, JJ.]

Land Acquisition Act, 1894 – ss.4(1), 6 – In 1943, Go vt. of India requisitioned 4 acres and 34 gunthas of land bearing Survey No. 120/2 (Part) of Village Malad, Mumbai – In 1949, 2. 68 acres land out of the aforesaid land was de-requisitioned – In 1975, notification was issued u/s.4(1) acquiring the said extent of 8623 sq.m. – Declaration u/s.6 issued in 1978 – Draft Awar d passed in 1986 – Challenge made in the present case in the year 200 2 – In a proceeding concerning other lands covered by the sa me s. 4 notification, Supreme Court in Kulsum R. Nadiadwala v. State of Maharashtra and Ors. , allowed appeal by land owner – In view thereof, present case referred to larger Bench that delay and laches have to be ignored – Held: On facts, question of delay a nd laches need not be answered as s.4 notification that was str uck down in Kulsum R. Nadiadwala’s case is the very notification in the facts of this case wherein the entire acquisition proceedings were quashed – Unable to agree with appellant’s contention that the s.4 notific ation not only deals with various other lands in Village Mal ad but also deals with a land in a different village altogether viz., Village Wadhawan, and that Supreme Court’s judgment did not go to the extent of declaring the acquisition bad so far as village W adhawan is concerned – So far as village Malad is concerned where the land in Kulsum R. Nadiadwala’s case was land that was adjacent to the present land, the very s.4 notification was struck down and decl ared null and void – This being the case, it would not be in the int erest of justice to allow the present appeal in favour of ap pellant, as this would amount to a discrimination between two person s who are otherwise similarly placed – Further, Kulsum R. Nadiadwala’s case did not deal with newspaper publication at all – It only d ealt with the requirement of publication in the Official Gaze tte and public [2020] 3 S.C.R. 765 765 A B C D E F G H 766 SUPREME COURT REPORTS [2020] 3 S.C.R.

notices of the substance of the notification being given in the locality in which the lands are acquired, both of which were held to be cumulative and mandatory requirements of s.4 – Given the fact th at this is a Defence project in which possession has b een with the Union since 1942, the same facts would obtain as in Kulsum R.

Nadiadwala’s case in which relief was granted – Therefore, present case cannot lead to a different conclusion on similar facts – Defence of India Rules, 1939 – r. 75A – Constitution of India – Arts. 141 and 142.

Dismissing the appeal, the Court

HELD: 1.1 Though this Court has, by its order dated 27.03.2018, referred this case to a larger Bench in view of the decision in Kulsum R. Nadiadwala ’s case that delay and laches have to be ignored, the Court is of the view that on the fa cts of this case, the Court need not answer this question. This is for the reason that the Section 4 notification that was struck down in Kulsum R. Nadiadwala ’s case is the very notification in the facts of this case. In Kulsum R. Nadiadwala ’s case, this Court quashed the entire acquisition proceedings stating that they be declared as null and void. Unable to agree with the contention t hat the Section 4 notification not only deals with various other l ands in Village Malad but also deals with a land in a diffe rent village altogether viz., Village Wadhawan, and that this Court’s judgment did not go to the extent of declaring the acquisition b ad so far as village Wadhawan is concerned. So far as village Ma lad is concerned, where the land in Kulsum R. Nadiadwala ’s case was land that was adjacent to the present land, the very Section 4 notification has been struck down and declared null and void, and this being the case, it would not be in the inter est of justice to allow the present appeal in favour of the Union of India, as this would amount to a discrimination between two persons who are otherwise similarly placed. [Para 8][772 G-H; 773 A-D] 1.2 Even though newspaper publication of the Sectio n 4 notification came in by amendment for the first time in 1984, the requirement of public notice where the land is situat e in addition to publication in the Official Gazette, was always there from the inception. Kulsum R. Nadiadwala ’s case did not deal with A B C D E F G H 767 newspaper publication at all. It only dealt with the requi rement of publication in the Official Gazette and public no tices of the substance of the notification being given in the localit y in which the lands are acquired, both of which were held to be cu mulative and mandatory requirements of Section 4. In Indore Development Authority ’s case, the Constitution Bench is seized of severa l questions, all of which pertain to the construction of Se ction 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. Thu s, it is wholly unnecessary to adjourn this case in order to aw ait the judgment of the Constitution Bench in this case. Given the fact that this is a Defence project in which possession has been with the Union since 1942, the same facts would obtain as in Kulsum R. Nadiadwala ’s case in which relief has been granted to Kulsum R. Nadiadwala . This case, therefore, cannot lead to a different conclusion on similar facts. It is important to make a di stinction between a declaration of law which would bind other future c ases under Article 141 of the Constitution of India and an ord er made in the facts of the case which may equally be made to do substantial justice on the facts of a given case, sometimes under Artic le 142.

In Kulsum R. Nadiadwala , though the appellant’s claim was restricted to only 50 per cent of the land in question, s o far as the other 50 per cent is concerned, the judgment itself makes a reference to the fact that the appellants are legal heirs of one deceased Ismail Nadiadwala and that there was another claima nt whose name was Ibrahim Nadiadwala to whom, presumably, 50 per cent of the property went. Since only Ismail Nadi adwala’s heirs were prosecuting the appeal, this direction appears to have been made. [Paras 10-15][774 B-H; 775 A-B] Kulsum R. Nadiadwala v. State of Maharashtra and Ors.

(2012) 6 SCC 348 : 2012 (7) SCALE 212 – relied on.

Indore Development Authority v. Manohar Lal and Others Etc. [2019] 14 SCALE 470 – referred to.

Case Law Reference

2012 (7) SCALE 212 relied on Para 3

[2019] 14 SCALE 470 referred to Para 6

UNION OF INDIA & ORS. v. GOPALDAS

BHAGWAN DAS & ORS.

A

B

C

D

E

F

G

H

768 SUPREME COURT REPORTS [2020] 3 S.C.R.

CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3636 of 2016.

From the Judgment and Order dated 31.07.2015 corrected on 11.09.2015 of the High Court of Judicature at Bombay in Writ Petition No.1667 of 2002.

Ms. Rekha Pandey and Arvind Kumar Sharma, Advs. for the Appellants.

Shyam Diwan, Sr. Adv., Y . Raja Gopala Rao, Ms. Y . Vismai Rao and Bhav Ratan, Advs. for the Respondents.

The Judgment of the Court was delivered by R. F. NARIMAN J.

1. This matter has a somewhat chequered history.

2. In 1943, Government of India requisitioned 4 acres and 34 gunthas of the land owned by one Rajabahadur Bhagwandas Harida s, bearing Survey No. 120/2 (Part) of Village Malad, Mumbai, in exercise of powers conferred under Rule 75A of the Defence of India Rule s, 1939. On 27.07.1949, the Collector, Thane, de-requisitioned 2.68 acres in the Survey No. 120 Part 2 out of the aforesaid 4 acres 34 gunthas.

Ultimately, despite the land having first being requisitioned, a notification under Section 4(1) of the Land Acquisition Act, 1894 (hereinafter referred to as ‘Act’), was issued on 24.10.1975 acquiring the aforesaid extent of 8623 square meters. A declaration under Section 6 of the Act was issued on 30.11.1978. According to the respondents herein, a Draft Award was passed under Section 11 of the Act on 23.09.1986, a gainst which references were made, both under Section 18 and 30, of the Ac t. The respondents confirmed that after symbolic possession was taken on 06.01.1987 by the State, such possession has remained with the State till date.

3. In a proceeding that was filed, insofar as other lands in Village Malad were concerned, covered by the same section 4 notification, this Court in Kulsum R. Nadiadwala v. State of Maharashtra and Ors.

(2012) 6 SCC 348, allowed an appeal by the land owner. After stating in paragraph 2 that the very same section 4 notification was issued in order that a Central Ordinance Depot for the Union of India be made for defence purposes, the judgment records that the benefic iary of these lands, being the Central Government, was served, but did not appear at A B C D E F G H 769 the time of hearing of the appeal. The appellant in Kulsum R.

Nadiadwala ’s case (supra) argued several points before this Cour t, which were resisted by the learned counsel appearing for the State of Maharashtra, basically on the ground that the writ petition should have been dismissed on the ground of delay and laches as was done by the impugned High Court judgment. After setting out Section 4 of the Act, this Court observed that the requirement that the notification under Section 4 be published in the Official Gazettee and the require ment that the Acquiring Authority should publish public notices of the substances of such notification in a convenient place or places in the locality in which the land proposed to be acquired is situate, are cumulative c onditions, both being mandatory. The Court then held: - “13. In the instant case, the respondents before the High Co urt had filed their reply affidavit. They did not dispute the contentions of the appellants that they had not issued any public notices as required under Section 4 of the Act. They only reiterated that such notification was published in the Official Gazette. Since the mandatory requirement as required under Section 4(1) of the Act is not complied with by the respondents, while acquiring the lands in question, in our opinion, the entire acquisition proceedings requires to be declared as null and void.

14. This Court in J&K Housing Board v. Kunwar Sanjay Krishan Kaul has observed that all the formalities of serving notice to the interested person, stipulated under Section 4 of the Act, has to be mandatorily complied with in the manner provided therein, even though the interested persons have knowledge of the acquisition proceedings. This Court further observed thus:

“32. It is settled law that when any statutory provision provides a particular manner for doing a particular act, the said thing or act must be done in accordance with the manner prescribed therefor in the Act. Merely because the parties concerned were aware of the acquisition proceedings or served with individual notices does not make the position alter when the statute makes it very clear that all the procedures/modes have to be strictly complied with in the manner provided therein. Merely because the landowners failed to submit their objections within 15 days after the publication of notification under Section 4(1) of the State Act, the authorities cannot be permitted to claim tha t it need not be strictly resorted to.”

UNION OF INDIA & ORS. v. GOPALDAS

BHAGWAN DAS & ORS. [R. F. NARIMAN J.]

A

B

C

D

E

F

G

H

770 SUPREME COURT REPORTS [2020] 3 S.C.R.

15. In view of the conclusion that we have reached on the f irst issue canvassed by the learned counsel for the appellants, we do not think that other issues that the learned counsel for the appellants has raised and canvassed before us need to be answered.”

4. It may only be mentioned that in Kulsum R. Nadiadwala ’s case (supra), the challenge was made by way of a writ petition filed in 1987, as opposed to the present challenge, which was made only in the year 2002.

5. Ms. Rekha Pandey, learned counsel appearing on behalf of the appellant, has raised several points in support of this appeal. First and foremost, she adverted to an order of this Court dated 27.03.2018 b y which a Division Bench of this Court has referred this matter to a larger Bench of three Judges. This order reads as follows:

“1. The land of the respondents was acquired vide notification dated 24.10.1975 under Section 4 of the Land Acquisition Act, 1894 (the Act). The said land was earlier requisitioned in the years 1942 to 1945 for defence purpose. Award was made in the year 1986 and symbolic possession of the land was taken on 06.01.1987.

Objections of the award were filed by the respondents again st the award. A reference under Section 18 of the Act was made which was disposed of. Thereafter, the writ petition was filed by the respondents mainly on the ground that there was no due publication of the notification under Section 4 of the Act which was a mandatory requirement.

2. The High Court upheld the plea of the respondents relying upon judgment of this Court in “Kulsum R. Nadiadwala Vs. State of Maharashtra” (2012) 6 SCC 348.

3. Learned counsel for the appellants submitted that having regard to the fact that the land was already being used for defence purpose since the year 1942 to 1945 and the notification under Section 4 issued on 24.10.1975 was challenged for the first time by the writ petition filed on 24.06.2002, the High Court should have dismissed the writ petition on the ground of delay and laches as entertaining such petition will seriously affect public interest. It was submitted that view taken in the relied upon judgment ignores the concept of laches.

A

B

C

D

E

F

G

H

771

4. Learned counsel for the respondents submits that in spite of delay and laches, this Court in the aforesaid judgment qua shed the acquisition.

5. We are of the view that delay and laches may be a bar t o challenge to the acquisition after 27 years. In Tamil Nadu Housing Board, Chennaiversus M. Meiyappan and ors (2010) 14 SCC 309 this Court held that inland acquisition proceedings the Court should not encourage stale litigation as it may hinder projects of public importance. The contra view in three-Judge Bench decision in Dayal Singh versus Union of India (2003) 2 SCC 593 was held to be in conflict with the Constitution Bench judgment in Rabindranath Bose versus Union of India (1970) 1 SCC 84 and three-Judge Bench judgment in Printers (Mysore) Ltd. versus M.A .

Rasheed(2004) 4 SCC 460. The said judgment was cited with approval in recent judgment of three-Judge Bench in Indo re Development authority versus Shailendra (Dead) through Lrs. & Ors. (Civil Appeal No.20982 of 2017 –pronounced on 8th February, 2018).

6. In view of above, the view taken by two-Judge Bench in Kulsum R. Nadiadwala versus State of Maharashtra (2012) 6 SCC 348 to the effect that delay and laches have to be ignored is not fre e from doubt.

7. Thus, we are of the view that the matter needs to be pla ced before a Bench of three Judges.

8. Accordingly, let the papers be placed before Hon’ble the Chief Justice of India for appropriate directions.”

6. Ms. Pandey, learned counsel, has argued before us that as a matter of law, such a huge delay in filing a writ petition against Section 4 notification cannot possibly be countenanced. She has also argued that in Kulsum R. Nadiadwala ’s case (supra), really speaking, the delay is only of one year, as the Award in this case was issued only in the year 1986, and the writ petition filed in that case was of 1987. In the present case, the writ petition, as has been stated earlier, was filed only in 2002.

Another important point of difference, according to the learned counsel is that notice was personally served on the respondents i n this case, which is not the case in Kulsum R. Nadiadwala ’s case (supra). She also raised the point that was raised in the special leave petition filed by UNION OF INDIA & ORS. v. GOPALDAS BHAGWAN DAS & ORS. [R. F. NARIMAN J.] A B C D E F G H 772 SUPREME COURT REPORTS [2020] 3 S.C.R.

the Union of India which is that Kulsum R. Nadiadwala ’s case (supra)

is “per incuriam” inasmuch as it decided a point which arose out of the Amendment Act of 1984, when the Section 4 notification was only of 1975, the 1984 Amendment Act not being retrospective. She further went on to state that, in any case, the Constitution Bench is taking up, as one of the pleas before it in Indore Development Authority v. Manohar Lal and Others Etc. (SLP (C) Nos. 9036-9038 of 2016) whether delay would apply as a good ground for dismissing a writ petition on the ground of laches insofar as challenges to land acquisition proce edings are concerned, and that we should await the judgment of the Constit ution Bench before proceeding with the judgment in this case. She kept harping upon the fact that the acquisition in this case is for important def ence purposes and possession of this land has been with the Union Government since 1942. She also stated that Kulsum R. Nadiadwala ’s judgment, if properly read, did not amount to quashing of the entire section 4 notification, particularly in view of the last paragraph of the judgment, where the claim of the appellant was restricted only to 50 per cent of the land in question, the direction being that the respondents shall hand over 50 per cent of the vacant possession of the said land to t he appellant forthwith.

7. As against these submissions, Shri Shyam Divan, learned senior counsel appearing on behalf of the respondents, argued that that the section 4 notification in both these cases being the same, and Kulsum R.

Nadiadwala ’s case being a final judgment of this Court in which a review petition and a curative petition have been dismissed, the said judgment would apply on all fours to the facts of this case. He pointed out that the question of delay, though raised by the learned counsel who appeared on behalf of the State, was not directly answered in Kulsum R.

Nadiadwala ’s case inasmuch as, according to the Division Bench of this Court in Kulsum R. Nadiadwala ’s case, a mandatory condition of a section 4 notification not being adhered to, would amount to there being no acquisition at all in the eye of law. On this ground, he defended the impugned judgment passed by the Bombay High Court.

8. Though this Court has, by its order dated 27.03.2018, referred this case to a larger Bench in view of the decision i n Kulsum R.

Nadiadwala ’s casethat delay and laches have to be ignored, we are of the view that on the facts of this case, we need not answer this question.

This is for the reason that the section 4 notification that was struck A B C D E F G H 773 down in Kulsum R. Nadiadwala ’s case is the very notification in the facts of this case. We may also note that in paragraph 13 of the Kulsum R. Nadiadwala ’s case set out hereinabove, this Court quashed the entire acquisition proceedings stating that they be declared as n ull and void.

We are unable to agree with Ms.Pandey’s contention that the Section 4 notification not only deals with various other lands in Village Malad but also deals with a land in a different village altogether viz., Village Wadhawan, and that this Court’s judgment did not go to the extent of declaring the acquisition bad so far as village Wadhawan is concerned.

So far as village Malad is concerned, where the land in Kulsum R.

Nadiadwala ’s case was land that was adjacent to the present land, the very section 4 notification has been struck down and declared null and void, and this being the case, it would not be in the interest of justice to allow the present appeal in favour of the Union of India, as this w ould amount to a discrimination between two persons who are ot herwise similarly placed.

9. Adverting to some of the other submissions made by Ms. Pandey, first and foremost, in Kulsum R. Nadiadwala ’s case, the High Court dismissed the writ petition filed therein on the g round of there being a 12 years delay in filing the writ petiti on, and not on the ground that there was a one year delay as the Award in thi s case was passed only in 1986. Secondly, the factum of notices actually b eing served in this case, as opposed to notices not being individually served in Kulsum R. Nadiadwala ’scase, apart from making no difference to mandatory conditions that have to be followed, as held in Kulsum R.

Nadiadwala , has been repelled by the judgment under appeal as follows:

“11. Nevertheless, we are dealing with the contentions raised by the First Respondent. Perusal of the Writ Petition and in particular Clause (h) of Paragraph 4 thereof shows that a specific contention has been raised by the Petitioners that neither the Petitioners nor their predecessors were served with any notice and were not offered any opportunity of raising objections to the Notification under Sub-section (1) of Section 4 of the said Act.

................................................... .............................. . .

................................................... .............................. . .

Affidavit of Shri Manoj Shankarrao Gohad, the Special Land Acquisition Officer (4) is completely silent as far as this f actual UNION OF INDIA & ORS. v. GOPALDAS BHAGWAN DAS & ORS. [R. F. NARIMAN J.] A B C D E F G H 774 SUPREME COURT REPORTS [2020] 3 S.C.R.

and legal challenge in this Petition is concerned.

… … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … .

… … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … … . ”

10. Insofar as the “ per incuriam” point is concerned, this can be disposed of by stating that even though newspaper publicat ion of the section 4 notification came in by amendment for the first time in 1984, the requirement of public notice where the land is situate in addition to publication in the Official Gazette, was always there from the inception.

Kulsum R. Nadiadwala ’s case did not deal with newspaper publication at all. It only dealt with the requirement of publicati on in the Official Gazette and public notices of the substance of the notif ication being given in the locality in which the lands are acquired, both of which were held to be cumulative and mandatory requirements of section 4.

11. So far as the Indore Development Authority ’s case (supra)

is concerned, the Constitution Bench is seized of several questions, all of which pertain to the construction of section 24 of the Right to Fa ir Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.

12. This being the case, and regard being had to what we have stated hereinabove, it is wholly unnecessary for us to adjourn this case in order to await the judgment of the Constitution Bench in this case.

13. Given the fact that this is a Defence project in which possession has been with the Union since 1942, the same facts would obtain as in Kulsum R. Nadiadwala ’s case in which relief has been granted to Kulsum R. Nadiadwala . This case, therefore, cannot lead to a different conclusion on similar facts.

14. As to the argument that no declaration that the entire section 4 notification is quashed inasmuch as the claim of the appellants in Kulsum R. Nadiadwala ’s case was restricted only to 50 per cent of the lands in question, it is important to make a distinction between a declaration of law which would bind other future cases under Article 141 of the Constitution of India and an order made in the facts of the case which may equally be made to do substantial justice on the facts of a given case, sometimes under Article 142.

15. On a reading of paragraph 16 of Kulsum R. Nadiadwala ’s judgment, it is important to note that though the appellant’s claim was A B C D E F G H 775 restricted to only 50 per cent of the land in question, so far as the other 50 per cent is concerned, the judgment itself makes a refe rence to the fact that the appellants are legal heirs of one deceased Ismail Nadiadwala and that there was another claimant whose name was Ibrahim Nadiadwala to whom, presumably, 50 per cent of the property went. Si nce only Ismail Nadiadwala’s heirs were prosecuting the appeal, thi s direction appears to have been made.

16. This being the case, we dismiss the appeal of the Union.

Divya Pandey Appeal dismissed.